Gantt Report shows Red bars on uncomplete tickets with end date after today

Symptoms

Gantt Report shows Red bars on uncomplete tickets with end date after today.

The following appears in the gadget:

 

Cause

This error was caused due to a bug on Gadget Utilities for JIRA versions prior to 4.2.8.

All of the following conditions must be met to reproduce the error:

  • The progress of a ticket is less than 100%

  • The year of the end dateof the ticket is greater than today's year

  • The month of the end date is less than today's month

 

https://eissoftware.atlassian.net/browse/EISUP-30

 

Work-around

Upgrade Gadget Utilities for JIRA to version 4.2.8