Gantt Report shows Red bars on uncomplete tickets with end date after today
Symptoms
Gantt Report shows Red bars on uncomplete tickets with end date after today.
The following appears in the gadget:
Cause
This error was caused due to a bug on Gadget Utilities for JIRA versions prior to 4.2.8.
All of the following conditions must be met to reproduce the error:
The progress of a ticket is less than 100%
The year of the end dateof the ticket is greater than today's year
The month of the end date is less than today's month
https://eissoftware.atlassian.net/browse/EISUP-30
Work-around
Upgrade Gadget Utilities for JIRA to version 4.2.8